Why electricity supply across Nigeria was limited on New Year day – Report
Out of a peak demand forecast of 17,720 MW on New Year day, 4,685 MW was generated.
Out of a peak demand forecast of 17,720 MW on New Year day, 4,685 MW was generated.
The current peak transmission surpassed the 5,155.9 MW attained on December 8.
The new record exceeds previous national peak record of 5,074.70 recorded on February 2.
The peak generation ever attained in Nigeria was 5,074.7MW.
Customers in Lugbe, Wuse II, Gwarimpa, Life Camp, Mabushi, and Mpape will benefit from improved supply.
The NNPC hopes to build independent power plants at various locations in the country.
Already, the state government has gas processing plant to supply the plant gas.
Transcorp seeks to raise the capacity of the plant to 2200MW by 2018.
Mr. Sani says until Nigerians have light, all so-called power reforms remain academic.
The Minister of Power, Chinedu Nebo, says there is a need for investors to key into the sector to realise ...
The fire was caused by a fallen petrol tanker. The Transmission Company of Nigeria, TCN, said it had lost one of ...
Sam Amadi spoke extensively on the new phase of Nigeria’s power industry The Federal Government has said the thrust of ...
There are currently about 10 planes in the presidential fleet. The Presidency is set to increase the number of private ...
TCN is also undertaking the installation of power transformers in other transmission substations nationwide. The Transmission Company of Nigeria, TCN ...
Power generation in Nigeria is now 4,500mw