12 Nigerian power plants produced Zero megawatt electricity on Christmas Day

Darkness with lantern

For millions of Nigerians who had no electricity on Christmas Day, a possible official reason has been provided.

The Nigeria Electricity Supply Industry, NESI, disclosed that about 12 power stations could not produce electricity during off-peak period during the holidays including on Christmas Day.

According to the News Agency of Nigeria, statistics from the National Control Centre, Osogbo, showed that Afam IV-V, Geregu Gas, Alaoji National Integrated Power Project (NIPP), and Olorunsogo Gas plants could not produce a single megawatt (MW) on December 25, 2016.

Others that could not produce a single megawatt (MW) on December 25, 2016 include Odukpani NIPP, Okpai, Ibom Power, ASCO, AES, Omoku, Rivers NIPP and Gbarain power plants.

The twelve plants have a combined capacity of 2,035 MW of Nigeria’s total installed power output of 11,165MW.

The Transmission Company of Nigeria, TCN, has also said that it on Wednesday wheeled out about 3,959 megawatts of generated electricity to the 11 distribution companies as the country’s power supply gradually stabilised.

The power generation data was obtained from daily forecast on the Nigerian Electricity System Operator (SO) website.

The daily power statistics posted by SO, a section of the TCN, shows that power generation gradually improved during the festive season with a peak generation of 3,959 megawatts from the national grid.

The website shows that the country’s power generation also recorded its lowest generation of 3,366 megawatts within the same period.

According to the NESI operational report for January 3, the power sector hit a peak generation of 4,959 megawatts as against 3,321 megawatts recorded on December 2.

NESI, a subsidiary of the TCN, said that the sector recorded highest system frequency of 51.52Hz and lowest system frequency of 48.85 Hz.

It also said that the highest voltage recorded was 372KV, while lowest voltage recorded on the same day was 300KV.

Meanwhile, NESI, on January 3 disclosed that over N534 billion of revenue was lost by the power sector in 2016.

Among the reasons for the loss are shortages in gas supply, frequency and line limitations and water levels management constraints that led to several cases of electricity outage in the country.

NESI, which put the average daily revenue loss at N1.5 billion, said gas constraint remained one of the major challenges facing the electricity sector.

It explained that the N534 billion amounts to the value of electricity lost on account of the challenges, part of which could have been used to bridge the liquidity gap in the power sector, estimated at N1trillion.

Already, the sector is finding it difficult to access more loans from Nigerian banks due to their inability to meet the payment obligations for previous debts.

The situation will also affect the capacity of the power firms to improve on electricity supply to consumers for domestic and industrial uses.

NESI said in its daily statistics on energy losses that the industry lost N1.525 billion on December 24, 2016 alone.


DOWNLOAD THE PREMIUM TIMES MOBILE APP

Now available on

  Premium Times Android mobile applicationPremium Times iOS mobile applicationPremium Times blackberry mobile applicationPremium Times windows mobile application

TEXT AD:DIABETES Is CURABLE! Don't Let It Threaten You! To NORMALIZE Your Blood Sugar In 21Days For Life, Click Here!!!.


All rights reserved. This material and any other material on this platform may not be reproduced, published, broadcast, written or distributed in full or in part, without written permission from PREMIUM TIMES.


  • O.C Noble

    There are some evil men and women supporting APC party inside Premium Times.
    When I wrote letter here that we are spending Christmas inside darkness and
    colliding with ourselves in the dark, those evil men cancelled my letter so that
    the world will not hear how bad President Buhari government has become.
    But now, after the evil men went on New Year holiday, the good people
    in Premium Times took second look at my letter and found out
    I was telling the truth.

  • Rommel

    The power companies should not tell us anything else until they hit at least 7000 MW, all these endless stories no longer offer good enough reason,power programs started under the obasanjo administration are yet to yield results almost 11yrs after the programs began,what type of people are Nigerians, are the power projects not another Ajaokuta steel complex?